How to Write a Technical Proposal for Government and Major Project Tenders

Evaluators score your technical offer against a sheet that was written before your file arrived. Here is how to build the proposal backwards from that sheet, section by section, and why layout matters most when offers are close.

By RX Editorial TeamNº 077October 31, 2026Updated October 31, 202613 min read
Share
TendersTechnical ProposalEtimadContractingBid Management
How to Write a Technical Proposal for Government and Major Project Tenders — RX Insights
Key takeaways
  • Where a Saudi government tender asks for separate technical and financial proposals, the technical ones are opened first, and only the financial proposals of accepted technical offers are examined.
  • Start with a compliance matrix built from the tender's own criteria, then write each section to answer one criterion with evidence.
  • Technical weights in construction are often low, but when prices are close a few technical points can decide the award.
  • A new Government Tenders and Procurement Law was issued by Royal Decree M/76, published in Umm Al-Qura on 4 September 2026; law firms report it takes effect around 2 January 2027. Check the official text and the status of its executive regulations before relying on old templates.

Most contractors write a technical proposal the way they write a company profile: who we are, what we have done, why we are the best choice. The evaluation committee does not read it that way. It reads with a score sheet in hand, criterion by criterion, and the sheet was fixed in the tender documents before your file arrived. Every page that does not answer a criterion earns nothing, and every criterion the committee cannot find an answer to scores low or fails.

This guide shows how to build the technical envelope backwards from that score sheet. It is written for contracting, MEP, operations and maintenance and engineering firms bidding for Saudi government and major project tenders, with notes on the new procurement law and on Egypt. It covers the document. Registration on portals is a separate task, done in the bidding company’s name; RX has handled supplier and tender registration for clients on Saudi platforms such as Etimad, and our guide to the vendor registration document pack covers that step.

How a Saudi tender is actually evaluated

Under Saudi Arabia’s current Government Tenders and Procurement Law, proposals submitted through the government portal (Etimad) are encrypted (Article 37). Where the tender requires technical and financial proposals separately, only the technical proposals are opened first (Article 44), and the committee then examines the financial proposals that belong to the accepted technical proposals (Article 46). The tender documents must set out the criteria for assessing, comparing and accepting proposals (Article 24). The law also requires an initial guarantee of 1% to 2% of the proposal value (Article 41). Check the current text of the law and the tender itself, because a new law replaces this one (see below).

On the portal itself, a bidding guide published by Setup in Saudi, a private consultancy, describes separate upload areas for technical documents, financial documents and attachments, with prices entered in an online bill of quantities. Treat that as a general description rather than an official rule: follow each tender’s instructions, because the required files and upload structure can differ between tenders.

How the two halves are combined is set out in the controls for preparing bid evaluation criteria (Arabic, version 1.0, March 2021), issued by the Expenditure Efficiency and Government Projects Authority (EXPRO) under the executive regulations and published on the Ministry of Finance site. Three rules in it shape how you should write:

  • Some criteria are pass/fail. Examples in the guide include meeting the key technical specifications, committing to the required delivery or service schedule, providing a time-bound work plan and, where required, a certified local content baseline and target. A bid that fails one can be excluded, however good the rest of it is.
  • There is a minimum technical score. The entity sets the minimum mark a technical offer must reach before its financial offer is evaluated, and it may set minimums for individual criteria. The guide’s worked example uses a 70% pass mark as an illustration, not a fixed rule; the actual figure is whatever the tender states.
  • Weights are set in advance. The criteria and their weights are set out in the tender documents, so read them before you plan the proposal.

What the weights mean for your effort

The same guide sets ranges for the technical and financial weights by contract type. Selected ranges from the 2021 version (check the version current when you bid, and the weights stated in your tender):

Contract typeTechnical weightFinancial weight
Construction, high value10% to 30%70% to 90%
Construction, below high value5% to 20%80% to 95%
Operations and maintenance, specialised, high value50% to 70%30% to 50%
Consulting, high value60% to 80%20% to 40%
Routine or simple supplyPass/fail only100%

A low technical weight in construction tempts many firms to treat the technical envelope as paperwork. That is a mistake for two reasons. First, the pass mark still applies, so a careless technical offer can remove you before price is considered. Second, the scoring is relative. In the guide, a bidder’s technical score is its average points divided by the highest average among the offers, and its financial score is the lowest price divided by its own price.

Hypothetical example (illustrative figures, not a real tender or client). Take a construction tender weighted 20% technical and 80% financial. Bidder A scores 90 technical points, the highest, and prices at SAR 10.0 million. Bidder B scores 72 points and prices at SAR 9.6 million, the lowest. Bidder A gets 20 (full technical) plus 76.8 (9.6 divided by 10.0, times 80), a total of 96.8. Bidder B gets 16 (72 divided by 90, times 20) plus 80, a total of 96.0. Bidder A wins while charging about 4% more. When offers are close, the technical envelope can decide the award.

Start with a compliance matrix, not a template

Before anyone writes a paragraph, build a compliance matrix from the tender documents. It is a table with one row for every requirement and evaluation criterion, taken word for word from the terms, the scope of work, the specifications and the evaluation section. For each row, record:

  1. the clause or criterion reference and its weight or pass/fail status;
  2. the exact wording of the requirement;
  3. where your answer sits in the proposal (section and page);
  4. the evidence attached (certificate, CV, reference letter, plan);
  5. the owner inside your company and the status;
  6. any deviation or clarification needed.

Hypothetical example (a sample layout, not a real tender). The first five rows of a matrix for a maintenance tender might look like this:

Ref.Requirement wordingWeight or statusProposal section and pageEvidenceOwnerClarification
EC-1“Provide a time-bound work plan covering the full contract period”Pass/failSection 4, p. 18Programme (Gantt) and manpower histogramPlanning engineerAsk whether mobilisation counts within the period
EC-2“Methodology and method statements for each major activity”25 pointsSection 3, pp. 9–17Method statements, inspection and test plansOperations managerNone
EC-3“CVs of key staff meeting the stated qualifications”20 pointsSection 5, pp. 19–31CVs, professional registrations, availability lettersHR, project directorConfirm whether a named alternate is accepted
EC-4“Project-specific health, safety and environment plan”10 pointsSection 7, pp. 36–41HSE plan, risk assessments for key activitiesHSE managerNone
EC-5“Certified local content baseline and target”Pass/failSection 8, p. 42Certificate and target form in the required formatCommercial managerConfirm the form version

The matrix does three jobs. It shows gaps early, while there is still time to send questions through the clarification channel. It becomes the proposal’s structure, because each section should map to one or more rows. And a short version of it, placed at the front of the technical proposal, tells the evaluator exactly where to find each answer. Older Saudi procurement regulations did not allow bidders to amend the tender terms or add reservations to their bids. Check what the current tender documents allow, and treat any deviation as something to resolve through clarifications, not something to slip into the text.

The technical envelope, section by section

The evaluation criteria guide lists typical technical criteria with example point ranges: methodology and project management, work plan and schedule, team qualifications, relevant experience, knowledge transfer, quality management, health, safety and environment, Saudisation and local content. The table below maps each to what an evaluator needs to see.

SectionWhat earns pointsCommon weakness
Understanding of scopeA restatement of the project’s objectives, constraints and interfaces in your own words, showing you read the site and the specificationsCopying the scope of work back to the client
Methodology and method statementsStep-by-step sequence for each major activity: resources, equipment, inspection and test points, approvals, risks and how they are controlledGeneric method statements reused from another project with the old project name still inside
ProgrammeA time-bound plan that meets the required duration, with milestones, critical path, procurement lead times and approval durationsA bar chart that does not match the methodology or the manpower plan
TeamOrganisation chart, named key staff, CVs that match the role requirements, professional registrations and availability commitmentsLong CVs with the relevant project buried on page three
Experience and referencesSimilar projects with value, scope, client, dates, your role and a contact or completion certificateA list of logos with no scope or value
Quality managementThe quality plan for this project: document control, inspection and test plans, non-conformance handling, handoverAttaching a certificate instead of a project plan
Health, safety and environmentA project-specific HSE plan: risk assessment for key activities, permits, site rules, training, incident reportingA corporate policy page and nothing else
Local content and SaudisationThe baseline and target in the required form (see our guide to presenting ICV and local content), the local suppliers and subcontractors, the Saudi workforce planStatements of intent with no numbers

Two rules apply across all sections. Write to the criterion, using its wording in your headings so the evaluator can match them. And keep every number consistent: the manpower in the method statement, the programme and the organisation chart must agree, because evaluators can cross-check them, and inconsistency reads as a proposal assembled by people who did not talk to each other.

Presentation: why it affects scores

Evaluators are typically engineers and procurement staff reading several long proposals against the same sheet. Presentation does not replace substance, but it decides whether substance is found and credited. In practical terms:

  • Navigation. A contents page, the compliance matrix, numbered sections that follow the criteria order and clear file names on upload.
  • Hierarchy. One idea per heading, short paragraphs, tables for comparisons, and a two-line summary at the start of each major section stating what you commit to.
  • Visual evidence. Organisation charts, sequence diagrams, site logistics plans and annotated photos of comparable work explain faster than text.
  • Consistency. One template, one terminology and one set of names across all volumes, in the language the tender requires. A coherent document signals a coherent company.
  • File discipline. Respect the portal’s formats and size limits, and keep searchable text rather than scanned images where you can, so evaluators can find and copy what they need.

This is where a proper proposal template system pays back: once the structure, layouts and standard sections exist, each new tender becomes an exercise in tailoring content rather than rebuilding a document. RX Designer’s business solutions and sales enablement work includes proposals, technical and financial offers and tender and pre-qualification files, built on the client’s brand identity so every submission looks like the same established company. For Azeidk, a contracting and electromechanical company working across Saudi Arabia and Egypt, that work includes company presentation content, service summaries, offers and project document content, built on a service architecture used across the website, the company profile and every campaign. The client reviews and approves the content, and its authorised users submit on the portal. If you are still at the pre-qualification stage, see our guide to the company profile that wins pre-qualification.

Decide bid or no-bid before you write

A strong technical proposal takes senior time, and the worst use of that time is a tender you could not win. Score each opportunity before you buy the documents, or at the latest before you assign a team. A simple sheet, rated 1 to 5 per factor, is enough:

  • Fit: does the scope match work you have done at a similar size, and can you show references for it?
  • Pass/fail exposure: can you meet every mandatory requirement, including classification, certifications, local content and the schedule?
  • Team: are the key staff the tender requires available and qualified on paper?
  • Weighting: does the technical weight reward your strengths, or is this effectively a price contest?
  • Commercial capacity: can you carry the initial guarantee, the final guarantee and the cash flow?
  • Time: is there enough time to the deadline to produce a tailored proposal and get clarifications answered?

Set a threshold in advance and stick to it. If your record shows a run of losses, read why you keep losing tenders even when your price is lower before the next bid. Firms that bid less often but write every proposal to the criteria tend to do better than firms that submit lightly edited copies to every tender they see.

The new procurement law, and a note on Egypt

Saudi Arabia’s Council of Ministers approved a new Government Tenders and Procurement Law in August 2026, as announced by the Ministry of Finance. The law was issued by Royal Decree M/76, published in Umm Al-Qura on 4 September 2026; law firms report it takes effect around 2 January 2027 (Baker McKenzie). Baker McKenzie’s October 2026 note said only a draft of the new executive regulations had been released for consultation at the time. Check the official text of the law and the current status of the regulations before relying on these dates. Changes reported by Al Tamimi & Company and Clyde & Co that matter to bidders include:

  • the bid opening and bid evaluation committees merge into a single committee, and the Local Content and Government Procurement Authority may take part in evaluation;
  • bid validity changes from 90 calendar days to 90 working days;
  • the direct purchase threshold rises from SAR 100,000 to SAR 1 million, and the final guarantee exemption threshold rises from SAR 100,000 to SAR 300,000;
  • separate frameworks on localisation and knowledge transfer, and on research and innovation procurement, are to follow.

None of the commentary we reviewed details changes to how technical proposals are scored, which will sit in the executive regulations and supporting guidance. Check each tender’s documents and the Ministry of Finance’s rules and regulations page rather than assuming last year’s template still fits.

Egypt. Under Law No. 182 of 2018, bids are submitted in separate technical and financial envelopes and financial envelopes are opened only for technically accepted bids (Article 23, per an unofficial English translation by Andersen; the Arabic text governs). Our guide to technical offers for Egyptian government tenders covers the rest.

Before submission, run one last check against your compliance matrix: every row has an answer and evidence, every pass/fail item is clearly met, the numbers agree across volumes, the guarantee is in the required form, and the authorised signatory has approved the final files.

Frequently asked questions

What is the difference between the technical and financial proposal in a Saudi tender?

The technical proposal shows how you will deliver: methodology, programme, team, experience, quality, HSE and local content. The financial proposal contains your prices, usually entered in the bill of quantities. Where they are submitted separately, the technical proposals are opened and evaluated first, and only the financial proposals of accepted technical offers are examined.

How much do technical scores count in government tenders?

It depends on the contract type and is stated in the tender documents. EXPRO's evaluation criteria controls (version 1.0, 2021) set ranges, for example 10% to 30% technical weight for high-value construction contracts and 60% to 80% for high-value consulting. The entity also sets a minimum technical score that an offer must reach before its price is evaluated.

What is a tender compliance matrix?

A table listing every requirement and evaluation criterion from the tender documents, with where your proposal answers it, the evidence attached, who owns it and any clarification needed. It is used to find gaps, to structure the proposal and, in a short version, to help evaluators locate each answer.

Does the new Saudi procurement law change how I should write proposals?

The new law was issued by Royal Decree M/76, published in Umm Al-Qura on 4 September 2026; law firms report it takes effect around 2 January 2027. In October 2026 only a draft of its executive regulations had been released. Reported changes include a single bid opening and evaluation committee and bid validity measured in working days. Check the official text, each tender's documents and the current regulations before reusing old templates.

Sources
  1. Ministry of Finance, Saudi Arabia, Government Tenders and Procurement Law.
  2. Expenditure Efficiency and Government Projects Authority, published by the Ministry of Finance, Saudi Arabia, Controls for Preparing Bid Evaluation Criteria (Arabic), version 1.0 (2021-03-18).
  3. Ministry of Finance, Saudi Arabia, New Government Tenders and Procurement Law: Rules and Regulations.
  4. Ministry of Finance, Saudi Arabia, Implementing Regulations of the Government Tender and Procurement Law (older regulations, 2007) (2007-03-10).
  5. Baker McKenzie, Saudi Arabia: Key changes under new government procurement law (2026-10-21).
  6. Al Tamimi & Company, Key changes to Saudi Arabia's newly adopted Government Tenders and Procurement Law (2026-09-23).
  7. Clyde & Co, Saudi Arabia's new Government Tenders and Procurement Law: An Overview of the Key Reforms (2026-10-01).
  8. Ministry of Finance, Saudi Arabia, Saudi Minister of Finance thanks leadership for Cabinet approval of the new Government Tenders and Procurement Law (2026-08-05).
  9. Setup in Saudi, How to Use Saudi Arabia's Etimad to Bid on Governmental Contracts (2026-02-04).
  10. Andersen in Egypt, Law No. 182 of 2018 regulating contracts concluded by public entities (unofficial English translation).
Share
Last updated October 31, 2026
About RX InsightsRX Insights is written by the RX Editorial Team at RX Designer, a marketing and business solutions studio working with companies in Saudi Arabia, Egypt, the UAE and Qatar. Articles are researched with AI-assisted tools, checked against the sources listed above and reviewed by our team before publication. Spotted something that needs correcting? Email studio@rx-designer.com.
Keep reading

Related insights

All insights
Expert Guide·Branding & Identity·SAUDI ARABIA

The Company Profile That Wins Pre-Qualification: Structure and Evidence

Pre-qualification evaluators score your profile against criteria fixed in advance, often with pass/fail gates. This is a section order, evidence standard and layout that help them find every answer fast.

Nº 033October 31, 202613 min read