- In UAE federal tenders a supplier without an ICV certificate scores zero on ICV; Abu Dhabi's 2021 guideline (v1.0) gives local content 40% of the financial criterion.
- UAE, Saudi, Qatari and Omani programmes ask for different documents; name the programme every time and never merge them into one score.
- State certified figures exactly, with entity name and expiry date, and keep future commitments visibly separate.
- Keep one master local value sheet per legal entity and update the profile, pre-qualification template and proposals from it.
Most suppliers treat their ICV certificate or local content figures as a compliance attachment: obtained once a year, uploaded to a portal, then forgotten. Yet in many Gulf tenders that number is scored, and the way it is presented decides whether an evaluator finds it, trusts it and credits it. This guide is not about how to get certified. It is about using the local-content standing you already have in the documents buyers read: the company profile, the pre-qualification file, the proposal and your public channels.
A note before starting: programmes and tender terms change, and each buying entity applies them under its own policy. Treat everything below as a working guide, not legal advice: check the current rules and the specific tender documents, and take legal or audit advice where the stakes justify it.
Why local content is now a scored line, not a footnote
Three examples show how much weight these credentials can carry.
- UAE federal tenders. The Ministry of Industry and Advanced Technology (MoIAT) says certification is optional for federal government tenders, but “the ICV score will be calculated as zero if the supplier does not provide an ICV certificate”. You can still bid; you simply forfeit that part of the score.
- Abu Dhabi government procurement. The first edition (version 1.0, October 2021) of the Department of Government Support’s local content guideline sets local content at 40% of the financial criterion in technically and financially evaluated tenders, with price taking the remaining 60%. Its own example: where the financial weight is 70%, local content is worth 28% of the total score. A bidder that does not submit a certificate is not excluded but scores zero on local content. We found no later edition published online as of October 2026, so confirm the version your tender applies.
- Saudi government procurement. According to a Clyde & Co briefing of September 2026, the local content preference regulations give national products a 10% price preference (competing foreign products are evaluated as if priced 10% higher), government entities are generally required to comply with the Mandatory List of national products administered by the Local Content and Government Procurement Authority (LCGPA), and in certain designated procurements bidders may have to disclose their local content baseline and commit to a target. Some designated procurements also use evaluation mechanisms that take a bidder’s local content profile into account. The government encyclopaedia Saudipedia (2023) gives a specific weighting for local content in bid evaluation, but we could not confirm that figure in the current regulation or a law-firm source, so take the weighting from each tender’s own evaluation criteria. The Ministry of Finance also put proposed amendments to the preference regulations to a public consultation that closed in January 2025; check which version is in force.
To see what that means in points, take the Abu Dhabi formula: local content weighted score = local content weight × the rating on your certificate. As an illustration with hypothetical figures, in a tender where local content is worth 28 points, a supplier whose certificate shows 30% earns 8.4 points, one showing 45% earns 12.6, and one with no certificate earns zero. When offers are close on price, a gap of about four points can decide the award. That is why a certificate nobody can find in your file is a commercial problem, not an administrative one, and one of the quieter reasons in our diagnosis of why tenders are lost.
Four programmes, four different documents
The biggest presentation mistake in the region is treating “ICV” as one thing. Each market, and often each buyer, asks for something different. The table summarises what we could verify on official or reputable sources.
| Market | Main framework | What the buyer usually needs from you | Presentation point |
|---|---|---|---|
| UAE | National ICV Program, governed by MoIAT; started at ADNOC in 2018 and extended to federal level in 2021 | A valid ICV certificate per legal entity, issued by an authorised certifying body from IFRS audited statements | Show the score exactly as certified, the legal entity name and the expiry date |
| Saudi Arabia | Local content preference regulations, administered by LCGPA, in government procurement; Aramco’s iktva programme for its supply chain | Compliance with the Mandatory List, a local content baseline and target where the tender designates it; for Aramco, iktva participation and a five-year action plan | Separate government local content figures from iktva material; never merge them into one “score” |
| Qatar | Tawteen ICV programme run by QatarEnergy for the energy sector | ICV performance assessed under Tawteen for QatarEnergy and energy-sector tenders; check the buyer’s current certification requirement | Position it as an energy-sector credential, not a national certificate |
| Oman | ICV in government tenders, led by the Tender Board; JSRS certification for oil and gas suppliers | Local investment and spend commitments in government contracts; an active JSRS certificate for oil and gas operators | Lead with commitments and Omanisation evidence, plus the JSRS status where relevant |
UAE: one certificate, many buyers, different rules of use
ADNOC, where the programme has run since the beginning of 2018 before MoIAT announced its federal expansion in September 2021, states that suppliers need only one ICV certificate per legal entity, accepted by all participating entities, but that implementation is “unique at each entity level”. MoIAT’s supplier guidelines (June 2021) set out the same validity and per-licence rules summarised in the box above. Aldar’s ICV page asks for the entity’s latest certificate, which it labels Version 3.0, in bid submissions, so check which certificate version each buyer expects. One score travels, but the buyer’s own tender terms decide what it is worth.
Saudi Arabia: commitments matter as much as the current figure
Saudi local content works differently. Instead of one portable score, the emphasis in designated procurements, as we read the Clyde & Co summary, is on your baseline today and the target you commit to deliver. Clyde & Co note that the regulations provide for financial penalties for certain breaches and that serious or repeated violations can be referred to the procurement law committee, which can bar a contractor from government contracts. A new Government Tenders and Procurement Law has since been issued (Royal Decree M/76, published in Umm Al-Qura on 4 September 2026; law firms report it takes effect around 2 January 2027); the Clyde & Co briefing says its effect on the local content framework “remains to be seen”. Check the current regulations before you quote any rule in a proposal.
Qatar and Oman: sector-led rather than national
QatarEnergy says suppliers that invest in ICV “gain a competitive edge in tenders issued by QatarEnergy”, assessed on local purchases, capability development and capital investment. In October 2024 it announced an enhanced programme with a refined formula, a bonus scheme and a simplified certification process for micro and small enterprises; the report gave no start date for the changes, so check whether they apply to your tender. The sources also disagree on when Tawteen ICV began: QatarEnergy’s own page says it was launched in 2020, while the press report refers to the original programme launched in 2019. We have not resolved the difference, so avoid quoting a launch year in your documents. In Oman, we could not open an official government page on ICV in tenders, so the picture rests on secondary sources. The US government’s country commercial guide (published December 2025) reports that ICV is embedded in government tenders in all sectors and requires companies to invest in Oman a minimum of 10% of the government contract’s value. The state-owned Oman Observer reported in October 2024 that the General Secretariat of the Tender Board leads a National Local Content Policy (2024–2030) approved by the Council of Ministers, including a mandatory list of national products and services. In oil and gas, bidders also need an active JSRS certificate: according to Business Gateways, which operates JSRS, the Ministry of Energy and Minerals mandated it for all suppliers bidding in the sector from 1 July 2021. Confirm the current requirement with the Tender Board or the buying entity.
Where each credential belongs in your documents
Evaluators read different documents for different reasons. Put the credential where the question is being asked, in the form that answers it.
| Document | What to include | What to leave out |
|---|---|---|
| Company profile | A short “Local value” page: certified ICV score per entity with validity date, local workforce share, local facilities, local suppliers you buy from, training programmes | Tender-specific commitments and figures that will expire before the profile is replaced |
| Pre-qualification file | The certificate itself, a one-line summary in the compliance matrix, registration numbers that match the commercial licence | Marketing language around the score |
| Technical proposal | Your localisation plan for this contract: local subcontractors, local manufacturing or assembly, national hiring and training, how you will report | Claims you cannot evidence during execution |
| Commercial offer | The certificate or baseline exactly as the tender requests, in the envelope it requests | Anything that duplicates or contradicts the technical envelope |
| Website and LinkedIn | The story behind the number: the factory, the national team, the training academy, the local partners | Certificate scans, exact scores that will date quickly, any client data |
Our earlier guide to the company profile for pre-qualification covers section order and evidence in general. For local content, the specific rule is simple: one clearly labelled page or table, placed where the evaluation criteria sit, never buried in “About us”. The localisation plan belongs in the technical envelope; our guide to writing the technical proposal shows where it sits in the structure.
Turn the score into evidence, not a boast
An ICV percentage on its own says little to a procurement committee that sees dozens of them. What persuades is the substance behind it. Under MoIAT’s guidelines, the UAE certificate scores manufacturers on local manufacturing cost and service providers on third-party spend in the country, and both on investment in the UAE, Emiratisation and expatriate contribution, plus a capped bonus that can reward, among other things, exports after local value addition. Each of those maps to something you can show:
- Local spend: the share of materials and services bought from in-country suppliers, and named categories (for example, “steel fabrication and electrical panels sourced locally”).
- Investment: facilities, warehouses, workshops and equipment you own in the country, with locations.
- Nationalisation: national headcount, roles at management and technical level, and training or graduate programmes.
- Manufacturing or assembly: what is made or assembled locally, and what is imported.
Hypothetical example: a facilities-management contractor bidding for a ministry maintenance contract in Riyadh, with a modest current baseline, might win more credibility by showing a dated plan (Saudi supervisors trained and certified by a named month, spare parts bought through two named in-Kingdom suppliers, a local call centre opening in the second contract year) than by rounding its figure up. In our view, suppliers that start from a low baseline are better served by a believable, dated route upwards than by an inflated number.
Six presentation mistakes that cost points
- The expired certificate. With a 14-month validity tied to the audited statements, a UAE certificate can lapse between audit cycles. Put the expiry date next to the score everywhere it appears.
- The wrong entity. A group score quoted for a subsidiary, or a Dubai licence’s certificate attached to an Abu Dhabi entity’s bid. Every name and licence number must match the bidding entity.
- Confusing score and weight. “40% ICV” in a profile can be read as your score or as the tender’s weighting. Write it out in full, for example “Certified ICV score: 32.5% (valid until …)”, using your own certified figure.
- Mixing programmes. An iktva action plan, a UAE ICV certificate and a Tawteen certificate are not interchangeable. Name the programme each time.
- Arabic and English versions that disagree. In bilingual files, figures and entity names must be identical in both languages.
- Different numbers in different documents. The profile says one figure, the proposal another, LinkedIn a third. Keep one master source and update everything from it.
Communicating local value beyond the tender file
Procurement teams, consultants and main contractors check suppliers before invitations go out. Your public channels should make the local-value story easy to find, without publishing documents that belong in the bid. Useful content includes national hiring and training milestones, facility openings, local partnerships with suppliers who have agreed to be named, and plain explanations of what you manufacture or assemble in the country. Keep claims general where figures will date quickly, and make sure anything you say publicly matches the certified position.
Executives’ LinkedIn profiles carry this story in a form people read: a managing director posting about the first cohort of national technicians, or a new local workshop, gives evaluators context the certificate cannot. Keep any figure in a post identical to the certified one, or leave the figure out. Our guide to executive LinkedIn covers what to post and how often.
Who owns it, and a routine that keeps it current
Local content touches finance (audited statements), HR (nationalisation data), procurement (local spend), sales (proposals) and marketing (profile and channels). Without an owner, each keeps its own version. A routine we suggest:
- Keep one master “local value sheet” per legal entity: programme, score or baseline, certificate number, issue and expiry dates, and the supporting facts.
- Diarise renewal well before expiry (we suggest at least two months), aligned with the audit timetable.
- When a new certificate or baseline is issued, update the profile page, the pre-qualification template, the proposal boilerplate, the vendor-registration documents and public channels in the same week.
- Before each submission, check the tender’s own local content clause: which document, which envelope, which programme.
RX prepares company profiles, pre-qualification files and proposal content for B2B companies; the certification stays with the company and its certifying body, and portal accounts stay in the company’s name; on Saudi platforms such as Etimad, RX has also handled supplier and tender registration for clients. The practical next step is to take your last submitted file and check three things against this guide: is the certified figure on one labelled page, does every entity name match the bidding licence, and are commitments dated and kept apart from achievements? Building that “Local value” page and the matching compliance-matrix line is part of our tender and pre-qualification file work and company profile design; a business diagnosis session is the place to go through one live file together.
Frequently asked questions
Is an ICV certificate mandatory for UAE government tenders?
MoIAT says certification is optional for federal tenders, but a supplier that does not provide a certificate gets an ICV score of zero. Each participating entity applies the certificate under its own policy, so check the tender terms. This is general information, not legal advice.
How long is a UAE ICV certificate valid?
According to MoIAT, 14 months from the date of issue of the audited financial statements it is based on. Recertifying with the same statements does not extend that period.
Can a group use one ICV certificate for all its companies?
Not under MoIAT's guidelines, which treat each licence as an independent legal entity even under the same ownership, so each bidding entity needs its own certificate. Branches in the same emirate with identical activities and ownership, listed on the licences, can receive one combined certificate.
Does a UAE ICV certificate count in Saudi Arabia or Qatar?
No. Saudi government procurement applies its own local content preference regulations, administered by LCGPA, and Aramco runs its own iktva programme; Qatar's energy sector uses QatarEnergy's Tawteen ICV programme. Present each credential under its own programme name and check each buyer's current requirements.
Where should local content appear in a company profile?
On one clearly labelled page: certified score or baseline per entity with its validity date, plus the facts behind it such as local facilities, national workforce, local suppliers and training. Keep tender-specific commitments for the proposal.
- Ministry of Industry and Advanced Technology, UAE, In-Country Value (ICV) FAQs.
- Ministry of Industry and Advanced Technology, UAE (via u.ae), National In-Country Value (ICV) Certification Guidelines for Suppliers (2021-06).
- ADNOC, ICV Unified Certification Process.
- Department of Government Support, Abu Dhabi (hosted by EAD), Local Content Guideline in Government Procurement, First Edition (v1.0) (2021-10).
- Aldar, ICV Program.
- Clyde & Co, Local Content in Saudi Public Procurement: Key Considerations and the Broader Localisation Landscape (2026-09-01).
- Saudipedia, How Does the Kingdom Support Local Content? (weighting figure not independently confirmed) (2023-05-05).
- Argaam, Finance Ministry seeks public input on local content preference policy amendment (2025-01).
- Saudi Aramco, iktva: In-Kingdom Total Value Add Program.
- QatarEnergy, Social and Economic Development (Tawteen).
- The Peninsula, QatarEnergy announces introduction of enhanced In-Country Value program (2024-10-07).
- International Trade Administration, US Department of Commerce, Oman Country Commercial Guide: Selling to the Public Sector (2025-12-18).
- Oman Observer, In-Country Value key to developing governorates across Oman (2024-10-03).
- Business Gateways International (JSRS operator), Introduction to JSRS.
- Umm Al-Qura, Royal Decree M/76 approving the Government Tenders and Procurement Law (2026-09-04).
- Baker McKenzie, Saudi Arabia: Key changes under the new Government Procurement Law (2026-10-21).